ITVC Global is a professional provider in Preheat and PWHT survices

During the welding process, the two metal pieces being joined are subject to extreme temperatures and can cause the crystalline structure of the metal to pass through various metallurgical phases. As a result, hardening (and embrittlement) of the metal can occur to varying degrees (usually dependent on carbon content). Heat treatment is designed to reduce the hardness in the heat affected zone of the metals and also increase ductility in these sections. Various pressure vessel codes contain the specifics regarding the procedures for post-weld heat treatment.

For PWHT services at construction site/ premise, we need to following the bellow steps:

 

-       Document review:

+     Design drawing sheet

+     Materials specification

+     Applied standards

+     PWHT procedure/ PWHT thermal chart (temperature and time of heating, soaking time, temperature & time of cooling)

-       To generate the PWHT procedure

-       Prepare the materials and equipment for PWHT services.

-       Survey for construction site and object for PWHT services.

-       Preparing work for PWHT

-    Inspection on surface of weld/ object for PWHT – installation the flexible Ceramic Pads operating at 45V, 60V, 80V, 230 V.

-       Arrange for electrical sources and position of PWHT machine.

-       Installation of thermal sensors

-       Rechecking the available of equipment before supplying the power sources

-       Inspection and calibration for controlling parts – for generating of thermal chart

-       Prefix of time and thermal parameter need to control during PWHT process

-       Carrying out of supplying power sources and controlling the thermal of PWHT object  as per prefix thermal chart.

-       Monitoring and controlling of thermal at PWHT objectt

-       Checking and double check of thermal between thermal at auto recorder and infrared thermometer

-       End of PWHT process (take out the thermal chart, remove of thermal separator, PWHT machine)

-       Maintaining of site record

-       Prepare of PWHT report

-       Prepare of work completion sheet – take signature of client

 

To request for the Preheat and PWHT survices - Please contact ITVC Global - you'll get useful advice and the best service.