Chemical Incident Prevention Plans under Circular 20/2013 — Historical Guidance

2015-12-07 02:24:11 | Lượt xem: 8473 | Inspection and verification

On 5 August 2013, the Ministry of Industry and Trade issued Circular 20/2013/TT-BCT on chemical incident prevention and response plans and measures. This article records its historical requirements; the circular ceased to have effect on 28 December 2017.

Historical document — Circular 20/2013/TT-BCT ceased to have effect on 28 December 2017. Law on Chemicals 69/2025/QH15 took effect on 1 January 2026. The thresholds, authorities and timeframes below describe former rules; current applications must be checked against the applicable legislation and implementing documents.
Energy and environmental management illustration
Illustration of energy and environmental management.

Cases requiring a plan under the former rules

Under the former rules, the following cases required a chemical incident prevention and response plan in the industrial sector:

  1. Investment projects producing, storing or using hazardous chemicals where the maximum quantity held at any one time met or exceeded the threshold in Appendix IV to Decree 26/2011/ND-CP. A plan had to be prepared before the project began operating.
  2. Facilities producing, trading, storing or using hazardous chemicals where the maximum quantity held at any one time met or exceeded the threshold in Appendix IV to Decree 26/2011/ND-CP.
  3. Chemical projects or facilities changing production capacity, storage quantity, scale, or the number or types of chemicals, where the maximum quantity held at any one time met or exceeded the threshold in Appendix IV to Decree 26/2011/ND-CP.
  4. Projects or facilities handling both chemicals requiring a plan and chemicals requiring prevention and response measures. A plan covering all those chemicals was required, without a separate measures document.

Appraisal and approval of plans

Cases requiring measures under the former rules


Plans were appraised by a council including representatives of the Ministry of Industry and Trade; provincial or municipal Departments of Industry and Trade; fire-prevention and firefighting authorities; environmental authorities; relevant economic-zone, industrial-park, high-tech-park, export-processing-zone or industrial-cluster management boards, where applicable; and specialists.

The former timeframe for plan appraisal and approval was 30 days from receipt of a complete, valid dossier. The Ministry of Industry and Trade was the competent approval authority.

Circular 20/2013/TT-BCT also specified cases requiring chemical incident prevention and response measures in the industrial sector:

  1. Chemical projects whose maximum chemical inventory at any one time was below the quantity limit in Appendix VII to Decree 26/2011/ND-CP. Measures had to be prepared before operations began.
  2. Chemical facilities whose maximum chemical inventory at any one time was below the quantity limit in Appendix VII to Decree 26/2011/ND-CP.
  3. Chemicals for which Appendix VII to Decree 26/2011/ND-CP did not specify a quantity limit. The circular originally took effect on 15 October 2013. Read the historical circular here.

The circular’s historical effective date

Sources and legal status

Circular 20/2013/TT-BCT

Official list of repealed instruments

Law on Chemicals 69/2025/QH15

ITVC GLOBAL · SERVICE ENQUIRIES

Discuss chemical-safety consultancy with ITVC

Share your requirements and preferred timing. ITVC will review your enquiry and discuss a suitable service scope.

Send a service request →

Call for quotation: 0914 564 579
Ho Chi Minh City: 0859 553 986
Email: itvc.haiphong@itvc-global.com

Head office: 6th Floor, 22 Ly Tu Trong, Hong Bang Ward, Hai Phong, Vietnam.




Copyright © 2014 ICTV. All Rights Reserved.

tư vấn iso, tu van iso, kiểm toán năng lượng, kiem toan nang luong

0914 564 579