Overall Equipment Effectiveness, or OEE, is widely used in Total Productive Maintenance (TPM). It measures equipment effectiveness through availability, performance and quality, helping an organisation identify opportunities for improvement.
Availability = Actual run time ÷ Planned production time × 100%.
Quality = Good units ÷ Total units produced × 100%.
Performance = Total units produced ÷ (Actual run time × Ideal production rate) × 100%.
OEE= Availability x Quality x Performance
When the factors are expressed as percentages, convert them to decimal fractions before multiplying, then express the result as a percentage. Use consistent time and production-rate units.
OEE is commonly calculated for individual equipment. When applying it to a production line, define the measurement boundary, the relevant constraint, planned production time, ideal rate and output count consistently. Adapt the measurement arrangement to the process without arbitrarily changing the meaning of the factors.
Discuss OEE implementation consulting and training with ITVC
Send your requirements so ITVC can advise on the service scope and provide a suitable quotation.
Send a service request →One of the main purposes of TPM and OEE improvement is to reduce the six big lossesthat account for much of the lost production effectiveness.

Breakdowns are often the most visible loss because they interrupt production unexpectedly. Examples include damaged dies or fixtures, unplanned maintenance, mechanical or electrical failures and equipment that cannot perform its required function or meet the operating specification.
This is an availability loss in OEE.
Setup and adjustment losses may be less visible because they are often accepted as a routine part of production. Examples include startup at the beginning of a shift, product changes, die or fixture changes, process-setting adjustments and material changes or shortages.
This is an availability loss in OEE.
Minor stops are short interruptions that usually do not require maintenance personnel. A threshold such as five minutes may be used locally, but it must be defined consistently. Examples include jams, blocked flow, feeding or alignment problems, incorrect materials, obstructed sensors and small downstream interruptions.
This is a performance loss in OEE.
Reduced-speed losses occur when equipment runs below its defined ideal speed. Causes can include unsuitable operating conditions or materials, worn or dirty components, incorrect settings and insufficient operator competence.
This is a performance loss in OEE.
Startup or adjustment can generate defective products as well as stop time. These defects may be scrapped or reworked immediately, or they may pass to later operations and cause additional quality problems.
This is a quality loss in OEE.
Production defects occur while equipment is otherwise considered to be operating normally. They include scrap, rework at the operation and defects detected later after non-conforming products have passed downstream.
This is a quality loss in OEE.
ITVC GLOBAL · SERVICE ENQUIRIES
Share your requirements and preferred timing. ITVC will review your enquiry and discuss a suitable service scope.
Call for quotation: 0914 564 579
Ho Chi Minh City: 0859 553 986
Email: itvc.haiphong@itvc-global.com
Head office: 6th Floor, 22 Ly Tu Trong, Hong Bang Ward, Hai Phong, Vietnam.
Copyright © 2014 ICTV. All Rights Reserved.
tư vấn iso, tu van iso, kiểm toán năng lượng, kiem toan nang luong